4th Five Year Plan
[ Home ]
<< Back to Index


Chapter-
1 || 2 || 3 || 4 || 5 || 6 || 7 || 8 || 9 || 10 || 11 || 12 || 13 || 14 || 15 || 16 || 17 || 18 || 19 || 20 || 21 || 22 || 23

Chapter 12:
POWER

The sources of electric power are large and varied. They are coal, oil, natural gas, atomic fuel and water. Low grade coal is ava liable in plenty, deposits of thorium useful as nuclear fuel occur in large quantities, and only a seventh of the potential water resources available has been harnessed for electricity at the commence. ment of the Fourth Plan. Lignite, natural gas and refinery gas are being utilised for power generation where they are available. Exploration for oil continues. The Atomic Energy Commission will establish a research and a prototype breeder reactor for providing thorium as an economic fissile material for power generation. Generation of low cost power, thermal or hydro, is as important as adequate generation. It is for this reason that large sized thermal power stations are being located near the collieries, washeries and oil refinaries. The effort to produce more and cheaper power is one on which the concerned organisations at the Centre and in the States are continually engaged. The Government has constituted a committee of technical experts to go into the question of effecting economies in the cost of generation, transmission and distribution of electricity. This committee's recommendations are expected to be available in 1970.

12.2. The progress in the generation of electricity has been significant :

Table 1 : Growth of Electricity Generation and Consumption

year installed generating capacity at the end of the year (mill. kw) ;

electricity generatedduring the year:(mill. kwh)

electricity consumed ; during the year (mill. kwh)

(1) (2) (3) (4)
1960-61 5.65 20123 16644
1965-66 10.17 36825 30366
1968-69 14.29 51700 41400

Average annual growth rate of generating capacity was 12.5 per cent during the Third Plan and 12.6 per cent during the three Annual Plan periods. The growth of installed capacity by type of plant is given below:

Table 2 : Growth of Installed Capacity by Type of Plan

Sl. No. item unit 1960-61 1965-66 1968-69
(0) 0) (2) (3) (4) (5)
1 installed capacity mil), kw 5.65 10.17 14.29
2 hydro mil!, kw 1.92 4.10 . 5.9
3 thermal mill. kw 3.40 5.65 7.88
4 diesel mill. kw 0.33 0.42 0.5
5 energy gnerated mill. kwh 20123 36825 51700
6 public utilities mill, kwh 16937 32990 47350
7 hydro mill. kwh 7837 15225 20744
8 thermal mill. kwh 8732 17441 26275
9 diesel mill. kwh 368 324 331
10 power units in industrial establishments 3186 3835 4350

12.3. A. number of schemes of power generation fell behind schedule during the Second and Third Plan periods. As against a target of 6.9 million kW of installed capacity for 1960-61 the actual capacity commissioned was 5.65 million kW. This led to power cuts and a staggering of loads in some regions. The target for the Third Plan was 12.69 million kW of installed capacity. The actual capacity commissioned was 10.17 million kW. The outbreak of hostilities in 1962 and 1965 and other factors delayed the implementation of the projects Power supply at the end of the Third Plan remained unsatisfactory. During the three Annual Plans priority was again accorded for the completion of the projects which were in advanced stages of construction. About 4.12 million kW of generating capacity, nearly equal to the total added during the Third Plan, was installed between 1966 and 1969. This appreciable addition, coupled with a slower rate of growth in demand, has made the power position at the beginning of the Fourth Plan on the whole satisfactory except for marginal shortages in some areas. Arrangements are being made to transmit surplus energy from the adjoining States to the deficit areas. The addition of generating capacity during the Third Plan in each State and during the three Annual Plans is indicated in Annexure I.

12.4. Interconnection between State grid systems enabling inter-State transfer of power, was a significant development during the Third Plan. The Riband power system in Uttar Pradesh was connected with the Bihar DVC-West Bengal grid. The Mysore grid was connected with Tamil Nadu, Andhra Pradesh and Kerala grids,The power supply in the Bihar-DVC-West Bengal region was causing concern in 1961 on account of large increase in demand from certain important industries and breakdowns in certain power plants. Surplus power available from the Riband power station was transmitted to the Bihar-DVC-West Bengal region. Similarly, in order to overcome the power shortage in Andhra Pradesh, Tamil Nadu and Kerala during 1965-66, surplus power from Mysore was made available. Construction of inter-State lines received priority during the three Annual Plans. Inter-State lines between Mysore and Maharashtra as well as between Madhya Pradesh and Maharashtra were established early in 1961. Delhi was able to supply surplus power to Uttar Pradesh and Haryana, and Ksrala commenced bulk supply of surplus power to Tamil Nadu through newly-constructed inter-State lines.

12.5. The Third Plan envisaged that all power stations should be inter-connected to form State, zonal or super-grids so that the generation capacities are pooled and used to the best advantage of the region. For formation of grids, the country has been divided into five regions, each with a Regional Electricity Board. The regions are :

Northern Jammu and Kashmir, Himachal Pradesh, Punjab, Haryana, Delhi, Uttar Pradesh, Rajasthan and Chandigarh.
Western Gujarat, Maharashtra, Madhya Pradesh, and Goa.
Southern Andhra Pradesh, Tamil Nadu, Mysore, Kerala and Pondicherry.
Eastern West Bengal, Bihar, Orissa and D.V.C,
North-Eastern Assam, Manipur, N.E.F.A. and Nagaland.

12.6. The progress on transmission schemes is as follows :

Table 3 : Progress of Transmission Schemes (circuit km)

year above 500 voli but up 1 ll/15k'S above ts 11/15 to kV bu f up to66/78

110k and it above

total
(1) (2) (3) (4) (5)
1960-61 102027 41960 13901 157888
1965-66 185969 76358 28491 290818
1968-69 (estimated) 291000 194200 485200

In the Third Plan, the additions made to transmission and distribution were not commensurate with the increase in generation capacity. Over the three Annual Plans, however, (he position has improved to some extent. The transmission systems need appreciable strengthening and improvement during the Fourth Plan period.

12.7. Rural Electrification has received increasing importance. At the end of the Second Plan 25,630 villages had been electrified. By the end of March 1969, the number of electrified villages increased to 71,280. Energisation of irrigation pump sets forms an important programme under rural electrification. By 1968-69 about 10,87,567 pumps were in operation as against about 513,000 sets in 1966 and 192,000 sets in 1961.

12.8. The per capita consumption of electricity was 38 kWh at the end of 1960-61. It increased to 61.4 kWh by the end of the Third Plan and to 79 kWh. at the end of 1968-69. Industry continues to be the largest consumer. There has, however been a significant increase in power consumption by agriculture during the past five years. Category-wise utilisation of electrical energy consumed is given in Annexure II.

Outlays

12.9. The outlay for power in the public sector in the Fourth Plan is Rs. 2447,57 crores. The distribution is as follows :

Table 4 :  Outlay for Power (Rs. crores)

Sl. No, item states union territories centre centrally sponsored total
(0) (1) (2) (3) (4) (5) (6)
1 generation 974.06 25.48 255.10 1254.64
2 continuing schemes 823.82 25.00 210.10 1058.29
3 new schemes 150.24 0.48 45.00 195.72
4 transmission and distribution 645.51 44.27 9.80 22.00 721.58
5 rural electrification 285.15 9.54 150.00 444.69
6 investigation and miscellaneous 14.35 2.49 9.82 26.66
7 Total(I, 4 to 6) 1919.07 81.78 424.72 23.00 2447.57

The private sector is expected to provide about Rs. 75 corres, primarily on strengthening of their distribution net work.

12.10. Within the outlay for the continuing generation schemes and new schemes the States would be able to add 6.937 million kW to their installed capacity. Major hydel projects such as Beas (Debar), Yamuna, Ramganga, Ukai, Subernarekha, Sharavatty, Idikhi, Balimela and laige thermal stations at Santaldih, Kothagudem, NasiK, Koradi, Dhuvaran and Ukti, will go iiito operation during the Plan period. Anncxure III gives the list of continuing schemes which are expected to yield benefits during this period. For the new-schemes, art outlay of Rs. 150.24 crores has been provided in the States Pian. These schemes are yet to be identified. With the formation of the regional grids and establishment of central load despatch stations, selection of new generation schemes would be so made as to fit with the load characteristics of the region and generaliy to serve the regional requirements as a whole.

12.11. In the State Plans, a provision of Rs. 645.51 crores has been made for transmission and distribuion programmes in view of the persisting imbalance between generating capacity and the transmission and distribution facilities. Also the States contemplete a programme of energising 12,50,000 irrigation pump sets during the Plan period. As such a large programme is feasible only if it is supported by an equally large programme of transmission and distribution, each State will have to ensure that the necessary transmission and transformation facilities are available. Emphasis has been laid on infer-State and inter-regional lines so that the power system in each region can be operated on an integrated basis. The regional power systems are proposed to be inter-linked to form an All-India grid within the Plan period. For constructing these lines, a provision ofRs. 22 crores is set apart as Cenetrally-sponsored programme. Normally only 220 KV lines are proposed to be included in this programme except in some-areas where 132 KV lines suit the longterm needs. A list of lines which are proposed to be taken up during the Plan period is at Annexure IV. For the operation of regional glids the establishment of central load despatching stations in each region will be nec^sary for which provision has been made.

12.12. Rural Electrification.—Within the States Plan provision of Rs. 285.15 crores for Rural Electrification Programmes, the States would be able to energise about 7,50,000 pump sets. A Rural Electrification Corporation with a Plan outlay of Rs. 150 crores has been set up in the public sector for financing selected rural electrification programmes in the States. This investment would supplement the States' programmes and enable them to energise additional 5,00,000 pump sets. State-wise distribution of the irrigation pump energisation programme is given in Annexure V.

12.13. The Union Territories depend largely on the neighbouring States for supply of power. Schemes in hand in the territories are expected to be completed during the Plan Period and add 0.17 million kW of installed capacity. No new generation schemes are included in their Plans. Out of Rs. 44.27 crores proposed to be invested on transmission and distribution in the Union Territories, about Rs. 29 crores will be for building up transmission and distribution system in Delhi only. 4000 pumpsets are expected to be energised in the Union Territories.

12.14. Centre's Programme.—The provision of Rs. 210 crores in the Central Plan on continuing generation schemes includes Rs. 120 crores on atomic power generation, Rs. 49.25 crores on the Badarpur thermal station, Rs. 38.85 crores on D.V.C. schemes, Rs. 2 crores on the Neyveli thermal station. The first atomic power station at Tarapur of 380 MW capacity has gone into operation in 1969. In the second station at Ranapratap Sagar, the first unit of 200 MW is expected to be commissioned by 1971, and the second unit about two years later. In the third station at Kalpakkam (400 MW), the first unit (200 MW) is expected to go into operation in 1973-74. A provision of Rs. 5 crores has been made in the Plan for advance action on a new atomic power station, the location of which has yet to be decided. The ninth thermal unit of 100 MW at Neyveli has gone into operation during 1969-70 and the station has now a total capacity of 600 MW. The D.V.C. programme includes installation of two thermal sets of 120 MW each at Chandrapura. The Badarpur thermal station of 300 MW installed capacity is expected to have its first unit in operation in 1971-72 and other two units are expected to follow in 1972-73. Three new Central projects Loktak hydro-electric project in Manipur, Baira-Siul hydro-electric project in Himachal Pradesh and Salal hydro-electric project in Jammu and Kashmir are included in the Central Plan. Loktak and Baira-Siul schemes are scheduled to go into operation towards the end of the Plan.

12.15. The Central generating stations would be feeding into their respective regional grids. The establishment of central stations will depend on the beneficiary States agreeing to a minimum offtake of power at optimum load factor order to ensure that central stations will be utilised fully and operated economically; to the establishment of suitable transmission systems and tariff for power sold.

12.16. Out of 9.264 million kW generating capacity being added during the Plan period, plant and equimpent foi about 4.859 million kW of capacity will be supplied by the indigenous public sector manufacturers and the balance would be from foreign sources. Also, about 3.37 million kW capacity plant and equipment would be in various stages of manufacture in these undertakings for supply to spillover State projects. In addition, plant and equipment for new generation schemes which are yet to be identified would be under manufacture in these factories. There is adequate capacity in the country for manufacture of other heavy electrical equipment and no import of such equipment is envisaged in future.

12.17. In Annexure VI, the distribution of Plan outlays for different power programmes and the additional benefits available from the schemes are indicated. On the basis of the outlay for power generation a net installed capacity of 23 nxllion kW can be achieved, allowing for retirement of 0.4 million kW of old and obsolete plant. Out of the 23 million kW capacity, 9.42 million kW will be from hydro, 12.95 million kW from thermal and 0.98 million kW from nuclear stations. The level of utilisation of available capacity is at present low. There is scope for improving efficiency of operation. For maximising utilisation of the available capacity and also for meeting the peak demands on their systems, some of'the States may have to resort to fuller utilisation of stand-by capacities. Integrated ' operation of State grid systems utilising inter-State lines should also be adopted for maximising benefits.

12.18. A number of hydro and thermal schemes will be under construction towards the end of the Plan. On completion during the Fifth Plan, these will provide an additional capacity of about 3.37 million kW. With a provision of about Rs. 200 croies on new generation programmes, additional generating schemes would be included in the Plan tor completion during the Fifth Plan period. Some of the major steam stations particulaily those located or under construction near washeries and collieries, are designed for development in stages. Additional units can be installed at these stations in shorter construction periods during the Fifth Plan.

12.19. Electricity Board Finances.—At present the financial working of most of the Electricity Boards is not satisfactory. The Electricity (Supply) Act requires the State Electricity Boards to review their operations from time to time with a view to becomming self-supporting. In some States, large part of the electricity generated is sold to bulk consumers below the cost of generation. The increase in the cost of materials, lubricants, fuels and wages has further increased the operation and maintenance expenditure of the Boards. A committee on the Working of the State Electricity Boards (Venkataraman Committee) was set up in 1964 for examining the financial working of the Electricity Boards. One of the recommendations made by the Committee was that in the first phase, the Boards should aim at revenues sufficient to cover operational and maintenance charges, contribution to the general and depreciation reserves and interest charges on the capital base. In the second phase, the Boards should aim at an overall return of 11 per cent (interest 6 per cent; general reserve j per cept; electricity duty 1^ per cent and net profit 3 per cent, after meeting the operation, maintenance and depreciation charges. The main endeavour of the Boards should be to build sufficient surpluses for re-investment for further growth by improved efficiency in operation, fuller utilisation of available capacity and rationalising tariffs. It is necessary to ensure that these recommendations are implemented by the State Electricity Boards.

12.20. Other programmes which have been included and for which provision has been made in the Plan are :

  1. preliminary survey of hydro power generation sites;
  2. research work connected with power generation, tiansmission and distribution;
  3. power equipment testing centres;
  4. consultancy service for power development;and
  5. training of thermal power station operating personnel.

12.21. A country-wide programme for carrying out pie-investment survey of hdyro electric sites is under implementation. New sites will be taken up foi investigation during the Plan period. The Central Board of Irrigation and Power together with Electricity Boards have set up 18 research units since 1961-62. Besides, research on certain problems is being carried out in the University of Roorkee and the Indian Institute of Science, Bangalore. In addition applied research on problems concerned with generation, transmission and disribution is being carried out in the Power Research Institute, Bangalore, and the Switchgear Testing and Development Station at Bhopal. Fault locators, methods of testing, transformer oils and 'hot sticks', developed by the Power Research Institute from indigenous materials have been of use to the State Electricity Boards in the operation of their systems. Provisions has been made for the extension of the Switchgear Testing Centre at Bhopal. An organisation has been set up in Central Water and Power Commission to provide consultancy service;, for authorities incharge of generation projects. The Plan provides for the extension of two training institutes for the operational personnel of thermal stations established at Neyveli and Durgapur.

ANNEXURE I Growth of Installed Capacity— Utilities and Self-generating
Industrial Establishments : 1960-61. 1965-66 und 1968-69 (in megawatts)

Sl. No. state/union territory 1960-61 1965-66 1968-69
hydro thermal total hydro thermal total 1 hydro thermal total
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 states 1814.1 2291.3 4105.4 3986.5 3811.5 7798.0 5799.49 5440.55 11240.04
2 Andhra Pradesh 124.6 103.6 228.2 154.0 153.0 307.0 272.90 361.10 634.00
3 Assam 9.3 10.1 19.4 45.5 115.5 161.0 48.76 109,50 158.26
4 Bihar 51.9 51.9 97.0 97.0 239.49 239.49
5 Gujarat 333.3 333.3 666.0 666.0 661.56 661.56
6 Haryana -- 108.47 89.19 497.66
7 Jammu and Kashmir 10.6 2.4 13.0 28.0 3.0 31.0 26.92 13.41 40.43
8 Kerala 132.5 4.8 137.3 192.0 5.0 197.0 545.00 1.60 546.60
9 Madhya Pradesh 34.5 198.1 232.6 46.0 269.0 315.0 122.00 582.44 704.44
10 Maharushtra 281.9 477.6 759.5 599.0 706.0 1305.0 844.32 794.72 1639.04
11 Mysore 185.4 12.9 198.3 431.0 30.0 461.0 788.40 11.55 799.95
12 Nagaland 2.00 2.00
13 Orissa 157.5 13.2 170.7 304.0 14.0 318.0 304.42 197.03 501.45
14 Punjab 273.2 24.5 297.7 662.0 53.0 715.0 660.70 21.07 681.77
15 Rajasthan 73.9 70.6 144.5 156.0 104.0 260.0 305.33 177.12 482.45
16 Tamil Nadu 431.0 102.0 533.0 899.0 102.0 1001.0 969.00 101.50 1070.50
17 Uttar Pradesh 92.5 304.9 397.4 462.0 452.0 914.0 477.76 893.90 1371.66
18 West Bengal 7.2 581.4 588.6 8.0 1042.0 1050.0 25.51 1183.37 1208.88
19 union territories 0.4 84.3 84.7 1.0 124.0 125.0 3.45 269.32 272.77
20 Delhi 76.3 76.3 112.0 112.0 - 251.82 251.82
21 Others 0.4 8.0 8.4 1.0 12.0 13.0 3.45 17.50 20.95
22 centre 104.0 420.0 524.0 104.0 1000.0 1104.0 104.00 1357.50 1461.50
23 D.V.C. 104.0 420.0 524.0 104.0 709.0 804.0 104.00 957.50 1061.50
24 Neyvcli 300.0 300.0 -- 400.00 400.00
25 total utilities (1+19+22) 1918.5 2795.6 4714.1 4091.5 4935.5 9027.0 5906.94 7067.37 12974.31
26 self-generating industrial establishments 3.0 933.0 936.0 3.0 1143.0 1145.0 3.00 1311.00 1314.00
27 grand lota! (25 + 26) (net availble in MIV) 1921.5 3728.61 565U.I 4094.5 6078.5» 10173.0 5009.94 8378.37' 14288 31
28 net available in million kw 1.92 3.73 5.65 4.09 6.08 10.17 5.91 8.38 14.29

'Includes 330 MW of diesel generating capacity. 'Includes 420 MW of diesel generating capacity. 'Includes 500 MW of diesel generating capacity.

ANNEXURE II Pattern of Utilisation of Electrical Energy Consumed   (including Consumption
in Self-generating Industrial Establishments) (in million kwh)

Sl.No class of utilisation 1960-61 1965-66 1968-69
(0) (1) (2) (3) (4)
1 domestic or resiiential light and small power 1492.3 2355.1 3597.8
2 commercial light and small power 847.7 1650.1 1978.2
3 industrial power 12388.2 22409.6 30483.3
4 traction 453.9 1154.3 1252.3
5 public lighting 193.2" 279.6 401.5
6 irrigation 832.9 1891.8 3289.3
7 water works and sewage pumping 436.2 625.2 797.6
8 Total energy sold 16644.4 30365.7 41400.0

ANNEXURE III Benefits in the Fourth Plan from Generation Schemes included in the Fourth Plan—Public Utilities

Sl.No. scheme benefits during fourth plan (in megawatts)
(0) (1) (2)
1 continuing schemes (2+56+62) 8269.4
2 states 6.377.4
3 Ramagundem thermal scheme extension (Andhra Pradesh) 62.5
4 Kothagudem thermal station extension Stage III (Andhra Pradesh) 220.0
5 Umiam H.E. scheme Stage II (Assam) 18.0
6 Garo Hills thermal station (Assam) 5.0
7 Namrup thermal station extension (Assam) 30.0
8 Gauhati thermal station (Assam) 30.0
9 Barauni thermal station (Bihar) 100.0
10 Pathratu thermal station (Bihar) 250.0
11 Kosi H.E. scheme (Bihar) 20-0
12 Pathratu thermal station extension (Bihar) 220.0
13 Subernarekha H.E. scheme (Bihar) 65.0
14 Dhuvaran thermal station extension (Gujarat) 280.0
15 Gas turbine (Gujarat) 54.0
16 Ukai H.E. scheme (Gujarat) 300.0
17 Upper Bari Doab canal H.E. scheme (Punjab) 45.0
18 Beas (Dehar Power station) (Haryana-Punjab-Rajasthan) 165.0
19 Faridabad thermal station extension (Haryana) 55.0
20 Kalakote thermal station (Jammu and Kashmir) 15.0
21 Chenani H.E. scheme (Jammu and Kashmir) 23.0
22 Sumbal H.E. scheme Stage I (Jammu and Kashmir) 22.0
23 Kuttiadi H.E. scheme (Kerala) 75.0
24 H.E. scheme (Kerala) 260.0
25 Ranapratap H.E. scheme (Madhya Pradesh and Rajasthan) 43.0
26 Jawaharsagar H.E. scheme (Madhya Pradesh and Rajasthan) 99.0
27 Satpura thermal station (Madhya Pradesh and Rajasthan) 62.5
28 Vaitarna H.E. scheme (Maharashtra) 60.0
29 Koyna H.E. scheme Stage III (Maharashtra) 320.0
30 Purii thermal station (Maharashtra) 60.0
31 Bhatgar and Vir H.E. schemes (Maharashtra) 25.0
32 Nasik thermal station (Maharashtra) 280.0
33 Koradi thermal station (Maharashtra) 240.0
34 Sharavathi H.E. scheme Stage II (Mysore) 178.2
35 Sharavathi H.E. scheme Stage TIT (Mysore) 178.2
36 Dzuza H.E. scheme (Nagaland) 1.5
37 Talcher thermal station (Orissa) 62.5
38 Balimela H.E. scheme (Orissa) 360.0
39 Parambikulam H.E. scheme (Tamil Nadu) 155.0
40 Basin Bridge thermal station (Tamil Nadu) 30.0
41 Ennore thermal station (Tamil Nadu) 330.00
42 Ennore thermal station extension (Tamil Nadu) 110.00
43 Kodayar H.E. scheme (Tamil Nadu) 100.0
44 Kundah H.E. scheme Stage IV (Tamil Nadu) 110.0
45 Vamuna H.E. Stage I (Uttar Pradesh) 28.0
46 Yamuna H.E. Stage 11 (Uttar Pradesh) 240.0
47 Obra thermal station (Uttar Pradesh) 100.0
48 Obra H.E. Scheme (Uttar Pradesh) 99.0
49 Ramganga H.E. scheme (Uttar Pradesh) 120.0
50 Harduaganj thermal station Stage IV (Uttar Pradesh) 110.0
51 Obra thermal Station extension (Uttar Pradesh) 300.0
52 Yamuna H.E. Stage IV (Uttar Pradesh) 10.0
53 Jaldhaka H.E. scheme (West Bengal) 9.0
54 Santaldin thermal station (West Bengal) 240.0
55 Little Ranjit H.E. scheme (West Bengal) 2.0
56 union territories 172.0
57 Indraprastha thermal station V Unit (Delhi) 55.0
58 Nogi H.E. scheme (Himachal Pradesh) 2.0
59 Bassi H.E. scheme (Himachal Pradesh) 45.0
60 Giri Bata H.E. scheme (Himachal Pradesh) 60.0
61 Gumti H.E. scheme (Tripura) 10.0
62 others (63 to 68) D.V.C. 1720.0
63 Chandrapura thermal station units IV and V (DVC) 240.0
central 1480.0
64 Neyveli thermal station extension (Tamil Nadu) 200.0
65 Badarpur thermal station (Delhi) 300.0
66 Tarapur atomic power station (Maharashtra and Gujarat) 380.0
67 Ranapratap Atomic power station (Rajasthan) 400.0
68 Kalpakkam atomic power station (Tamil Nadu) 200.0
69 new schemes . (70+50) 830.0
70 states 560.0
71 Bhatinda Thermal station (Punjab) 110.0
72 Ukai thermal station (Gujarat) 120.0
73 new unit in Bihar 110.0
74 new units in Uttar Pradesh 220.0
75 central 270.0
76 Loktak (Manipur) 70.0
77 Siul Baira (Himachal Pradesh) 200.0
78 Total (1+69) 9099.4

ANNEXURE IV List of Inter-State and filter-Regional Links proposed to be included in the Fourth Five Year Plan

Sl. No name of the link voltage and no. of circuits route length (km.)
(0) (i) (2) (3)
Inter-state links northern region
1 Giri-Yamuna 132KVS/C 40
2 Pathankot-Chenani 220KVS/C 115
3 Badarpur-Moradnagar 220KVS/C 32
4 Pinjore-Shimla 132KVS/C 60
western region
5 Satpura-Ambazari 220KVS/C 138
6 Chandni-Bhusawal 132 KV 88
(stringing 2nd circuit)
7 Navasari-Nasik 220KVS/C 53
southern region
8 Munirabad-Hampi 220KVS/C 26
9 Pamba-Kayattar 220KVS/C 100
10 Idikki-Udumalpet 220KVS/C 112
11 Ennore-Nellore 220KVS/C 141
12 Kundah-Mysore 220KVS/C 130
eastern region
3 Chandrapura-Santaldih 220KVS/C 56
14 Chandil-Joda 220KVS/C 135
15 Chandrapura-Durgapur (DVC)-Durgapur (W.B.) 220KVS/C 160
16 Noamundi-Joda 132KVS/C 20
17 Purnea-Siliguri 132KVS/C 176
north-eastern region
18 Badarpur-Jirighat 132KVS/C 64
19 Imphal-Bokajan 132KVS/C 143
inter-regional links
20 Belgaum-Kolhapur 220KVS/C 99
21 Mughalsarai-Dehri 220KVS/C 123
22 Alipurduar-Bongaigaon 132KVS/C 108
23 Upper-Sileru-Balimela 220KVS/C 40

ANNEXURE V  Outlay for Rural Electrification and Targets of Energisation of
Additional Pump sets hi the Fourth Five Year Plan

sl. no. state/union territory pumps energised by electricity upto end of no. of additional pumps likely to be energised during IV plan total no. of pumps energised by end of IV plan outlay on rural electrification within state plan during IV plan (Rs. crores
third plan 1968-69
(0) (1) (2) (3) (4) (5) (6)
1 states 508763 1079940 745815 1825755 285.15
2 Andhra Pradesh 57225 122321 50000 172321 15.00
3 Assam Nil 55 3200 3255 10.88
4 Bihar 10660 49375 89000 138375 36.00
5 Gujarat 17155 42088 15000 57088 6.00
6 Haryana 15220 45385 25000 70385 10.00
7 Jamrnu and Kashmir 104 162 120 282 1.00
8 Kerala 6957 13909 11250 25159 4.50
9 Madhya Pradesh 7314 24631 50000 74631 20.00
10 Maharashtra 44978 124961 100000 224961 25.00
11 Mysore 42371 91888 38670 130558 15.50
12 Nagaland nil nil nil nil 0.07
13 Orissa nil 477 1500 1977 6.05
14 Punjab 25296 59112 22500 81612 9.00
15 Rajasthan 6861 18795 35000 53795 14.00
16 Tamil Nadu 256594 410119 152165 562284 41.15
17 Uttar Pradesh 17591 75465 150000 225465 61.001
18 West Bengal 437 1197 2410 3607 10.00
19 union territories 4162 7607 4185 11792 9.54
20 Andaman and Nicobar Islands nil nil nil nil 0.55
21 Chandigarh 99 172 195 367 nil
22 Dadra and Nagar Haveli nil 41 nil 41 0.34
23 Delhi 678 2975 2500 5475 2.50
24 Goa, Daman and Diu 6 42 100 142 2.27
25 Himachal Pradesh 88 197 nil 197 1.21
26 Laccadive, Minicoy and Amindivi Islands nil nil nil nil 0.18
27 Manipur nil nil nil nil 0.79
28 N.E.F.A. nil nil nil nil 1.40
29 Pondicherry 3291 4178 1300 5478 nil
30 Tripura nil 90 92 0.30
31 total (1+19) 512925 1087547 750000 1837547 294.69
32 R.E.C. financing programme 500000 500000 150.00
33 grand total (.31+32) 512925 1087547 1250000 2337547 444.69

Targets in col. 4 correspond to outlays in col. 6. 'Tentative,

ANNEXURE VI Fourth Five Year Plan—Outlays and Benefits

Sl. No. state/union territory

outlay (Rs. crores)

total

benefits (megawatts)

generation schemes trans- mission and distribution rural electrification investigation and misc. additional benefits from generation schemes total instalie

(capacity by end of 1973-74

spillover benefits into the fifth plan from continuing schemes
continuing new total
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
1 states 823.82 150.24 974.06 645 51 285.15 14.35 1919.07 6937.4 18177.4 2899.5
2 Andhra Pradesh 86.50 86.50 31 00 15.00 0.50 133.00 282.5 916.5 840.0
3 Assam 10.02 4.00 14.02 11.93 7.00
3.88
1.73 34 68 3.881 83.0 241.3
4 Bihar 49.71 13.54 63.25 50.00 36.00 0.75 150.00 765.0 1004.5 65 0
5 Gujarat 55.70 15.10 70.80 32.20 6.00 1.00 110.00 754.0 1415.6
6 Haryana 40.53 40.53 29.99 10.03 80.52 111.0 608.7 198.0
7 Jammu and Kashmir 27.48 27.48 10.87 1.00 0 74 40.09 60.0 100.3 112.0
8 Kerala 47.35 1.40 48.75 24.00 4.50 0.50 77.75 335.1 881.6 130.0
9 Madhya Pradesh 8.24 20.16 28.40 28.10 20.00 0.50 77.00 108.5 812.9
10 Mysore 15.90 6.00 21.90 49.80 15.50 0.30 87.50 356.4 1156.3
11 Maharashtra 118.00 24.00 142.00 80.00 25.00 2.25 249.25 985.0 2624.0 240
12 Nagaland 0.36 0.36 1.56 0.07 0.28 2.27 1.5 3.5
13 Orissa 35.77 35.77 23.37 6.05 1.00 66.19 422.5 924.0
14 Punjab 49.61 24.32 73.93 36.00 9.00 0.15 119.08 239.0 920.8 407-0
15 Rajasthan 28.64 28.64 53.42 14.00 0.10 96.16 121.0 603.4 240.0
16 Tamil Nadu 69.00 11.00 80.00 34.00 41.15 0.35 155.50 835.0 1905.5 100.0
17 Uttar Pradesh 147.01 30.72 177.73 125.27 61.002 4.00 368.00 1227.0 2598.6 327.5
18 West Bengal 34.00 34.00 24.00 10.00 0.20 68.20 251.0 1459.9 240.0
19 union territories 25.00 0.48 25.48 44.27 9.54 2.49 81.78 172.0 444.8
20 Andaman and Nicobar Islands' 0.55 0.55
21 Chandigarh8 1.75 1.75
22 Dadra and Nagar Haveli3 0.34 —- 0.34
23 Delhi (M.C.D.+NDMQ 9.39 9.39 29.30 2.50 1.00 42.19 55.0 306.8
24 Goa, Daman and Dili 4.18 2.27 0.75 7.20 1
25 Himachal Pradesh 10.78 nil 10.78 2.85 1.21 0.60 15.44 107.0
26 Laccadive Minicoy Amindivi Islands 0.18 0.18
27 Manipur 0.11 0.28 0.39 1.97 0.79 3.15 '" 138. 8" —
28 N.E.F.A. - 1.40 1.40
29 Pondicherry —- 0.43 0.14 0.57
30 Tripura 4.72 0.20 4.92 3.79 0.30 9.01 10.0
31 central plan 210.10 45.00 255.10 31.80 150.00 9.82 446.72 1990.0 3451.5 470.0
32 Ministry of I and P (including Badar-pur) 49.25 30.00 79.25 22.00 150.00 9.47 260.72 570.0 570.0 270.0
33 Damodar Valley Corporation 38.85 38.85 9.80 0.35 49.00 240.0 1301.5
34 Neyveli Lignite P.S. 2.00 2.00 2.00 200.0 600.0
35 atomic power stations . 120.00 15.00 135.00 135.00 980.0 980.0 200.0
36 iofal(I+}9+31) 1058.92 195.72 1254.64 721.58 444.69 26.66 2447.57 9099.4 22073.7 3369.5
37 self generating industrial establishments 165.0 1479.0
38 retirement of old and obsolete plant 400.0 400.0
39 net at the end of fourth plan 8864.4 23152.7

For hill areas in Assam.; 'Provisional.; 'The installed capacity in 1973-74 of 138.0 MW is for all union territories except Delhi.

[ Home ]
^^ Top
<< Back to Index