AIRPORTS AUTHORITY OF INDIA
DEVELOPMENT OF AIRPORTS 
Monitorable Targets and Milestones for Year 2011-12

I. Investment in PPP Airports

S.
No.
Name of the Scheme Actual
2010-11
 Target for 2011-12 Target 1st qtr. for 2011-12
(Cumulative)
Achievement 1st qtr. (2011-12)
(Cumulative)
Target 2nd  qtr. for 2011-12
(Cumulative)
Achievement 2nd  qtr. (2011-12)
(Cumulative)
Target 3rd  qtr. for 2011-12
(Cumulative)
Achievement 3rd qtr. (2011-12)
(Cumulative)
Target4th   qtr. for 2011-12
(Cumulative)
Remarks
(Reason of Shortfalls)
1. CSI Airport, Mumbai  1647.00 2698.00 623.00 506.00 1218.00 928.00 1871.00 1461.00 2698.00 - Delay in getting approval of         state Govt. for relocation of Chattarapati Shivaji statue. Technical issue of instability of in structural steel.- Delay in relocation of various underground utilities such as MTNL communication cables, electrical power supply cables, etc., BMC main water supply lines, Mahanagar gas supply lines, HPCL fuel line etc.  
- Delay in clearances from local authorities for central kitchen and GSD, demolition of existing structures, etc. Delay in approval by Air India and other airlines for RoFS and LNB area.
2. IGI Airport, Delhi  117.00 223.86
 
7.50 11.05 34.83 48.67 115.46 82.11 223.86 - Few of the activities not yet started/completed.  Hence actual expenditure are lower than the planned expenditure.
3. RGI Airport, Hyderabad 0.98 51.01 23.91 4.99 35.79 9.10 46.54 14.32 51.01 - Few of the project expenses have been deferred or are under initial stages of finalization like RFQ or are at negotiation stage and likely to be finalized shortly.
4. Bengaluru Inter-national Airport, Bengaluru 64.04  605.00
 
36.00 92.04 129.00 128.00 310.00 250.33 605.00 - Terminal 1 (T1) Expansion- Due to delay in clearance from Ministry of Environment and Forest (MOEF), the actual work started from August, 2011 instead of June as planned initially.  There were certain structural changes in the design contemplated at execution stage, which delayed the construction work.
 - West Apron Expansion - Due to Sub-grade Deficiency in soil rectification work, the execution of the work got delayed-Sustaining Capital expenditure: - Deferment of certain capital expenditure planned based on business requirement and considering expansion
  Total 1829.02 3577.87 690.41 614.33 1417.63 1113.77 2343.00 1807.76 3577.87  

 

I. Investment in PPP Airports

 

AIRPORTS AUTHORITY OF INDIA
DEVELOPMENT OF AIRPORTS 
Monitorable Targets and Milestones for Year 2011-12
Investment in PPP Airports
S.No. Name of the Scheme Actual 2010-11 Expenditure 2011 -12
(Cumulative)
Target / Achivement
2nd Qtr
1 CSI Airport Target  1510.00 1218.00
Achievement 1647.00 928.00
2 IGI Airport Target  162.50 34.83
Achievement 117.00 48.67
3 Hyderabad Airport Target  0.40 35.79
Achievement 0.98 9.10
4 Bengaluru Airport Target  192.71 129.00
Achievement  64.04 128.90
TOTAL Target  1865.61 1417.62
Achievement 1829.02 1114.67