Ministry of Power
Monitorable Targets and Milestones for 2012-13

I. Capacity Addition (MW)

S.No. Project Description Particulars Item 2011-12 2012-13 Grand Total for  2012-13
Qtr.1 Qtr.2 Qtr.3 Qtr.4
1 Capacity Addition (MW) Central Target 5725 1237 1219 1582.3 2630 6668.3
Achievement 4770 2391 0      
State Target 4266 1115 515 505 1903 4038
Achievement 3761.2 750 0      
Private Target 7610 1455 2685 2315 795 7250
Achievement 11970.5 2125 2370      
Total Target 17601 3807 4419 4402.3 5328 17956.3
Achievement 20501.7 5266 2370