Ministry of Railways: Operational Targets
Progress on Monitorable Targets for the First Quarter of 2012-13
Program | Year | Cummulative Targets and Progress | Apr | May | Jun* | Remarks/Reasons for Shortfall in Q1 |
---|---|---|---|---|---|---|
Originating Loading (Million Tonnes) | 2012-13 | Target | 81 | 164.5 | 246 | IIP indices show 3,4% growth in core sector industries in May-June 2012. |
Achievement | 80.25 | 164.38 | 244.81 | |||
2011-12 | Actual | 233.66 | ||||
Freight NTKMS (Billions) | 2012-13 | Target | 53.643 | 108.942 | 162.916 | |
Achievement | 51.553 | 104.951 | 156.269 | |||
2011-12 | Actual | 154.5 | ||||
Originating Passengers (Millions) | 2012-13 | Target | 690.86 | 1414.33 | 2141.49 | Minor Shortfall due to drop on sub urban section of Central Railway due to discruption of traffic on 3 days in April. In Mar, 2012 6% additional pasengers opted for montly/quarterly seasons tickets in anticipation of rise in fares. |
Achievement | 686.29 | 1379.93 | 2103.01 | |||
2011-12 | Actual | 2039.82 | ||||
PKMs (Billions) | 2012-13 | Target | 88.309 | 180.786 | 273.736 | |
Achievement | 90.71 | 181.99 | 275.9 | |||
2011-12 | Actual | 261.83 | ||||
New Lines (Kms) | 2012-13 | Target | 24 | |||
Achievement | 24 | |||||
2011-12 | Actual | 95 | ||||
Doublings (Kms) | 2012-13 | Target | 18 | 33 | 69 | Due to slow progress by the executing agencies |
Achievement | 18 | 43 | 54 | |||
2011-12 | Actual | 20 | ||||
Gauge Conversion (TKM) | 2012-13 | Target | 41 | 59 | 92 | Due to slow progress by the executing agencies |
Achievement | 41 | 59 | 59 | |||
2011-12 | Actual | 36 | ||||
Electrification Projects (for Tracks) (RKM) | 2012-13 | Target | 20 | 80 | 150 | Slippage in achieving the target is due to shortage of Material (Steel and Copper). |
Achievement | 18 | 18 | 78 | |||
2011-12 | Actual | 68 | ||||
Workshops including Production Units (In Rs. crore) | 2012-13 | Target | 75 | 150 | 250 | Minor shortfall: Will be made good in the coming months. |
Achievement | 77.35 | 136.17 | 238.58 | |||
2011-12 | Actual | 130.16 | 184.34 | 261.06 | ||
Metropolitan Transport Project (In Rs. crore) | 2012-13 | Target | 142.03 | 284.03 | 473.36 | Achievement upto May 2012. Acquisition of land and delay in clearances from Civil authorities. |
Achievement | 16.04 | 81.09 | 81.09 | |||
2011-12 | Actual | 109.39 | ||||
Rolling Stock | ||||||
Locomotives (Nos.) | 2012-13 | Target | 44 | 95 | 146 | Shortfall in production of diesel locomotives is due to supply chain issues. The shortfall will be made good during the year. The production of locos is, in fact, more than last year's 1st Qtr. |
Achievement | 39 | 81 | 132 | |||
2011-12 | Actual | 32 | 71 | 115 | ||
Wagons (Nos.) | 2012-13 | Target | 1000 | 2200 | 3500 | Annual Target for this year is 16000 compared to 18000 of last year |
Achievement | 1722 | 2949 | 4162 | |||
2011-12 | Actual | 1810 | 3648 | 5219 | ||
Coaches (Nos.) | 2012-13 | Target | 198 | 495 | 794 | |
Achievement | 207 | 526 | 847 | |||
2011-12 | Actual | 247 | 508 | 822 | ||
* Provisional |
Progress on Monitorable Targets for the 2nd Quarter of 2012-13
Program | Year | Cummulative Targets and Progress | 1st Qrt | July | August | September | Remarks/Reasons for Shortfall in Q2 |
---|---|---|---|---|---|---|---|
Originating Loading (Million Tonnes) | 2012-13 | Target | 246 | 328.75 | 409.94 | 489.44 | The IIP indices for April- August 2012 show a growth of 2.8% as compared to 5.5% growth in April-August 2011 |
Achievement | 244.81 | 327.02 | 405.54 | 481.45 | |||
2011-12 | Actual | 233.66 | 313.32 | 389.09 | 459.36 | ||
Freight NTKMS (Billions) | 2012-13 | Target | 162.916 | 217.716 | 271.487 | 324.14 | |
Achievement | 156.269 | 208.489 | 260.008 | 309.819 | |||
2011-12 | Actual | 154.5 | 206.63 | 257.728 | 305.906 | ||
Originating Passengers (Millions) | 2012-13 | Target | 2141.49 | 2853.84 | 3560.27 | 4282.99 | Marginal Shortfall is on account of drop in growth in number of passengers on the suburban section of Central, Western and Eastern Railways. |
Achievement | 2131.05 | 2844.01 | 3567.51 | 4274.87 | |||
2011-12 | Actual | 2039.82 | 2732.26 | 3418.36 | 4120.75 | ||
PKMs (Billions) | 2012-13 | Target | 273.736 | 364.81 | 455.11 | 558.64 | |
Achievement | 285.3 | 371.88 | 464.56 | 554.51 | |||
2011-12 | Actual | 261.83 | 355.6 | 443.4 | 531.2 | ||
New Lines (Kms) | 2012-13 | Target | 24 | 24 | 24 | 76 | Due to failure of contracts. |
Achievement | 24 | 24 | 41 | 41 | |||
2011-12 | Actual | 95 | 121 | 121 | 121 | ||
Doublings (Kms) | 2012-13 | Target | 69 | 69 | 92 | 142 | Due to heavy monsoon and failure of contracts. |
Achievement | 54 | 54 | 93.1 | 120.1 | |||
2011-12 | Actual | 20 | 32 | 51 | 123 | ||
Gauge Conversion (TKM) | 2012-13 | Target | 92 | 92 | 92 | 103 | Due to heavy monsoon. |
Achievement | 59 | 59 | 70 | 70 | |||
2011-12 | Actual | 36 | 47 | 163 | 163 | ||
Electrification Projects (for Tracks) (RKM) | 2012-13 | Target | 150 | 220 | 330 | 450 | Slippage is due to shortage of Material (steel). However, it is 12.15% more than last year. The target is likely to be made good in Q3 and Q4. |
Achievement | 78 | 83 | 168 | 323 | |||
2011-12 | Actual | 68 | 68 | 89 | 288 | ||
Workshops including Production Units (In Rs. crore) | 2012-13 | Target | 250 | 335 | 425 | 515 | The Figure for Sept 2012 is not yet available but as per trends in the preceeding month, the target is likely to be surpasssed |
Achievement | 238.58 | 331.87 | 480.7 | NA | |||
2011-12 | Actual | 261.06 | 326.03 | 428.65 | 527.41 | ||
Metropolitan Transport Project (In Rs. crore) | 2012-13 | Target | 473.36 | 757.33 | 1041.3 | 1419.93 | The Figure for Sept 2012 is not yet available. Acquisition of land and delay in clearances from Civil authorities. |
Achievement | 81.09 | 277.04 | 399.47 | NA | |||
2011-12 | Actual | 109.39 | 246.07 | 267.33 | 368.85 | ||
Rolling Stock | |||||||
Locomotives (Nos.) | 2012-13 | Target | 146 | 197 | 249 | 301 | Shortfall is marginal. Will be made good. |
Achievement | 132 | 187 | 242 | 298 | |||
2011-12 | Actual | 115 | 164 | 209 | 259 | ||
Wagons (Nos.) | 2012-13 | Target | 3500 | 4800 | 6100 | 7500 | Above Target, Yearly target less than that of last year |
Achievement | 4162 | 5247 | 6956 | 8831 | |||
2011-12 | Actual | 5219 | 7321 | 9117 | 10752 | ||
Coaches (Nos.) | 2012-13 | Target | 794 | 1100 | 1398 | 1702 | Above Target |
Achievement | 847 | 1183 | 1520 | 1852 | |||
2011-12 | Actual | 822 | 1101 | 1380 | 1666 |
Proposal Quarterly Targets for Railways (2012-13):Transport Output
Q1 | Q2 | Q3 | Q4 | Total | |
---|---|---|---|---|---|
Originating Loading(MT) | 246 | 489.44 | 763.72 | 1038 | 1038 |
NTKM(billion) | 162.92 | 324.14 | 505.78 | 688 | 688 |
Originating Passenger Targets (million) | 214.49 | 4282.99 | 6511.89 | 8740.79 | 8740.79 |
PKM(billion) | 279.32 | 558.64 | 837.96 | 1117.29 | 1117.29 |
Progress on DFC against Targets for 2012-13
SL.No. |
Activity |
Target Date |
Achievement Date |
Remarks |
---|---|---|---|---|
1. | Approval of Business Plan | 30.06.2012 | 30.06.2012 | Business Plan has been finalized and approved by MOR. |
2. | Signing of concession agreement between MOR and DFCCIL | 30.05.2012 | - | The concession agreement needs approval from Ministry of Finance. This is under discussion with MOF. The reply of the query raised by MOF, has been sent by MOR on 22.06.2012 to Ministry of Finance. On receipt of MOF’s approval concession agreement will be signed. |
3. | Approval of Model EPC contract by MOR | It has been decided to go for lumpsum design and build contract for DFC construction and not EPC. Model document is not required to be approved by MOR. | ||
4. | Approval of Framework for adopting PPP mode in remaining parts of DFC | MOR has decided for adopting PPP model for construction of Sonnagar-Dankuni section of 538 Kms. The policy framework for this is under preparation. Financial modeling for the project is being carried out. | ||
*Since quarterly progress is not required to be reported, progress made up to the end of the quarter may be indicated in words under Remarks. |
Progress of work on Dedicated Freight Corridor (Eastern Corridor)
Package1 |
Package2 |
Package3 |
Package 4 |
Package 5 (MIS) |
Package 6 |
||
---|---|---|---|---|---|---|---|
Land Acquisition (in ha) | Target | 484 | 360 | 476 | - | - | |
Achievement | 484 | 355 | 476 | - | |||
Date of Issue of RFQ | Target | Issued | Oct’2012 | Issued | |||
Achievement | Issued on 17.7.2012 | ||||||
Date of Issue of RFP | Target | Issued | Dec’ 2012 | ||||
Achievement | Under Preparation | Apr’ 2012 | |||||
Apr’2012 | |||||||
Date of Award of Contract | Target | Sept’ 2012 | Sept’ 2012 | Sept’ 2012 | Sept’ 2013 | Mar’12 | Jun’ 2012 |
Achievement | 13 first stage technical proposals for CST Contract Bhaupur–Khurja was received on 30.03.2012. GC evaluation report and technical opinion from RDSO for alternate technical proposal finalized. DFCCIL evaluation report has been submitted to World Bank on 31.07.2012 for NOC. World Bank vide mail dated 24.08.2012 has forwarded preliminary observations for review by DFCC. Considering World Bank’s observations, supplementary evaluation report submitted on 07.09.12.World Bank has given its observation on 27.09.2012, clarifications have been sent to World Bank on 28.09.2012. Contract is expected to be awarded by November, 12. | - | Contract awarded on 29.03.2012. | Contract awarded on 20.07.2012. | |||
Date of completion | Target | Dec’ 2015** | Dec’ 2015* | Dec’ 2015* | Dec’ 2016** | Mar’17 | Dec’2013 |
Achievement |
Progress of work on Dedicated Freight Corridor (Western Corridor)(Progress as on 30.09.2012) |
||||||||
Name of Package | Name of Package1 ( Rewari – Madar) |
Name of Package2 (Madar – Ikbalgarh) |
Name of Package 3-A (Steel Bridges over Sabarmati to Mahi River) |
Name of Package3 Ikbalgarh to Makarpura (Vadodara) |
Name of Package4 (Electrical) |
Name of Package 5 (S and T) |
Name of Package (Construction of 54 Bridges Vaitarna – Bharuch) | |
---|---|---|---|---|---|---|---|---|
Land Acquisition (in ha) | Target | 1185 | 924 | 396 | 1102 | - | - | - |
Achievement | 1174 | 924 | 75 (20 E has been issued. However 20 F is held up as RRP of Kalol Ikbalgarh section, whose alignment was reviewed, is under finalization. After RRP finalization 20 F can be issued). | 1012 | ||||
Date of Issue of RFQ | Target | Issued (Finalized on 29.06.2012) | Issued (Finalized on 29.06.2012) |
Issued | Jun’2012 | Aug’2012 | Sept’2012 | |
Achievement | Issued | Single stage bidding decided with JICA. Bid document under preparation with DFCCIL | Single stage bidding decided with JICA. Bid document under preparation with DFCCIL. | |||||
Date of Issue of RFP | Target | Jun’2012 | Jun’2012 | Sep’2012 | Sept’2012 | Jan’2013 | Feb’2013 | |
Achievement | RFP issued on 30.06.2012. Bid submission on 30.10.2012. | RFP issued on 30.06.2012. Bid submission on 30.10.2012 | PQ (Pre- Quaification) finalized on 5.10.2012. RFP with JICA for NOC. Queries raised by bidders in pre-bid meeting of package 1 and 2 held on 27.7.2012 are to be incorporated in the bid document. Discussions between DFCCIL and JICA are on. | PQ applications submitted by 3 bidders on 4.9.2012, under evaluation. RFP is with JICA for NOC. Queries raised by bidders in pre-bid meeting of package 1 and 2 held on 27.7.2012 are to be incorporated in the bid document. Discussions between DFCCIL and JICA are on. | Single stage bidding decided with JICA. Bid document under finalization | Single stage bidding decided with JICA. Bid document under finalization | ||
Date of Award of Contract | Target | Nov’ 2012 | Nov’2012 | Mar’2013 | Mar’2013 | Sep’2013 | Sep’2013 | Feb’2009 |
Achievement | Bids submission on 30.10.12 | Bids submission on 30.10.12 |
Various Programs and Traffic Targets for 2012-13
S.N0. | Cummulative Targets and Progress | Cumulative 2011-12 (Provisional) | 2012-13 (Cummulative) | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Program | Q1 | Q2 | Q3 | Q4 | Total | |||||||||||
Apr | May | June | July | Aug | Sept | Oct | Nov | Dec | Jan | Feb | Mar | |||||
1 | New Lines (Kms) | Target if additional funds are made available | 24 | 41 | 93 | 98 | 165 | 367 | 437 | 637 | 850 | 850 | ||||
Targets* | 1075 | 24 | 76 | 143 | 263 | 349 | 509 | 750 | 750 | |||||||
Achievement | 727 | |||||||||||||||
2 | Doublings (Kms) | Target (as per Trend) | 20 | 40 | 80 | 110 | 180 | 200 | 260 | 440 | 540 | 700 | 864 | 864 | ||
Target* | 1017 | 18 | 33 | 69 | 92 | 142 | 147 | 246 | 346 | 479 | 645 | 900 | 900 | |||
Actual | 856 | |||||||||||||||
3 | Gauge Conversion (TKM) | Target (as per Trend) | 40 | 55 | 85 | 95 | 400 | 480 | 748 | 748 | ||||||
Target* | 867 | 41 | 59 | 92 | 103 | 450 | 550 | 850 | 850 | |||||||
Actual | 752 | |||||||||||||||
4 | Electrification Projects (RKM + TKM) | Target (as per Trend) | 20 | 80 | 150 | 250 | 360 | 500 | 600 | 750 | 900 | 1000 | 1250 | 1379 | 1379 | |
Target* | 1110 RKM + 220 TKM | 20 | 80 | 150 | 220 | 330 | 450 | 520 | 600 | 750 | 833 | 967 | 1200 | 1200 | ||
Achievements | 1165 RKM + 560 TKM | |||||||||||||||
5 | Workshops including Production Units (In Rs. crore) | Target | 1050 | 75 | 150 | 250 | 335 | 425 | 515 | 620 | 725 | 830 | 973 | 1116 | 1259 | 1259 |
Achievements | 1222.85 | |||||||||||||||
6 | Metropolitan Transport Project (In Rs. crore) | Target | 1052 | 142.03 | 284.03 | 473.36 | 757.33 | 1041.3 | 1419.93 | 1845.3 | 2270.7 | 2836.91 | 3405.51 | 3978.1 | 4733.21 | 4733.21 |
Achievement | 1016.44** | |||||||||||||||
7 | Rolling Stock | |||||||||||||||
a | Locomotives (Nos.) | Target | 580 | 44 | 95 | 146 | 197 | 249 | 301 | 354 | 406 | 460 | 517 | 573 | 630 | 630 |
Achievements | 582 | |||||||||||||||
b | Wagons (Nos.) | Target | 18000 | 1000 | 2200 | 3500 | 4800 | 6100 | 7500 | 8800 | 10100 | 11500 | 13000 | 14500 | 16000 | 16000 |
Achievements | 18357 | |||||||||||||||
c | Coaches (Nos.) | Target | 3786 | 198 | 495 | 794 | 1100 | 1398 | 1702 | 2029 | 2346 | 2683 | 3116 | 3544 | 4000 | 4000 |
Achievements | 3637 |
Monitorable Targets for DFC Projects (2012-13)
Activity | Target Date | Achievement Date | Remarks |
---|---|---|---|
Approval of Business Plan | 30.06.2012 | 30.06.2012 | Business Plan has been finalized and approved by MOR. |
Signing of concession agreement between MOR and DFCCIL | 30.05.2012 | - |
DEA has recently raised certain observations on the fundamental structure of the Concession Agreement which was evolved over the last 3 years. DEA has raised some critical issues with regard to the Concession Agreement which are being deliberated between MOR and DEA. The last meeting was held on 28.10.2012. Subsequently, comments of DEA were received vide DEA O.M. No F.No 14/2/2012-INF dated 5.9.2012. There were some factual inaccuracies in the DEA’s OM regarding the debt for DFC. It was mentioned that World Bank and JICA loan will not be more than Rs 15000 to Rs 16000 crore and the rest remains to be mobilized through GBS or market borrowings. Position has been clarified to DEA vide Rly Bd OM No 2009/Infra/6/9 Pt that out of the fund requirement of Rs 79,200 crore for Eastern and Western DFC, World bank and JICA loan are estimated at RS 48,172 crore. DEA has been requested to re-examine the case in the correct perspective vide letter dted 20.9.2012 and reminder dated 5.10.2012. |
Approval of Model EPC contract by MOR | It has been decided to go for lumpsum design and build contract for DFC construction and not EPC. Model document is not required to be approved by MOR. | ||
Approval of Framework for adopting PPP mode in remaining parts of DFC | MOR has decided for adopting PPP model for construction of Sonnagar-Dankuni section of 538 Kms. The policy framework for this is under preparation. Financial modeling for the project is being carried out. Target: PPP for the Sonnagar- Dankuni section to be awarded by 31st March 2013 |
Statement V
2011-12 | 2012-13 | Remarks | ||
---|---|---|---|---|
Targets | Achievements | Targets | ||
Elevated Rail Corridor, Mumbai | No target in 2011-12 | 1 (60 km) |
Investment of Rs.20,000 crore to be awarded by March, 2013 | |
Station Redevelopment (Nos.) | Concessions to be awarded | Nil | 5 | Concession to be awarded by March, 2013. |
Locomotive Manufacturing Units | Concessions to be awarded | Nil | 2 | Concession for Marowhra and Madhepura Loco factories to be awarded by September, 2012. |
High Speed Corridor | Mumbai-Ahmedabad option to be explored. | |||
Setting up of Accounting System | New target | Try to achieve in 2012-13 | Essential for accelerating reforms | |
Expansion of Container Train Operation | New target | Qualitative Direction | Increasing containerization of Rail traffic | |
1. Elevated Rail Corridor - Mumbai (60 Kms to be awarded by March, 2013 | ||||
2. Redevelopment Plan of Stations (5 Nos. to be awarded by March, 2013 | ||||
3. Concessions for the Marora and Madhepura Locl Factories to be awarded by September, 2012 | ||||
4. Highspeed Corridor of Mumbai--Ahmedabad - Options to be explored for development | ||||
5. Setting up of Accounting System - Efforts to be made to achieve prgoresss in 2012-13 | ||||
6. Expansion of Container train Operatons - To be expanded for increased containerisation of Rail Traffic |
Progress on DFC against Targets for 2012-13(Eastern Corridor)
(Progress as on 30.06.2012)
Sl.No. | Name of Package | Name of Package1 (Civil work for Bhaupur to Bhatura) |
Name of Package2 (Civil work Bhatura to Birauni) |
Name of Package3 (Civil Work Birauni to Khurja) |
Name of Package4 (Electrical and S and T) Bhaupur to Khurja) |
Name of Package 5 (MIS) | Name of Package 6 (Track works for NKWD-DGO 66 KM section) |
|
---|---|---|---|---|---|---|---|---|
Particulars | Length (kms) | 134 | 102 | 106 | 343 | 3338 | ||
1. | Cost (Rs. In crore) |
Estimated* | - | - | - | - | - | |
Awarded | 23.97 | |||||||
2. | Land Acquisition (in ha) | Target | 484 | 360 | 476 | - | - | |
Achievement | 484 | 340 | 466 | - | ||||
3. | Date of Issue of RFQ | Target | Issued | Oct’ 2012 | Issued | |||
Achievement | - | |||||||
4. | Date of Issue of RFP | Target | Issued | Dec’ 2012 | ||||
Achievement | - | Apr’ 2012 | ||||||
5. | Date of Award of Contract | Target | Sept’ 2012 | Sept’ 2012 | Sept’ 2012 | Sept’ 2013 | Mar’12 | Jun’ 2012 |
Achievement | 13 Bid received and are under Evaluation. Contract is expected to be awarded by September,12 | 13 Bid received and are under Evaluation. Contract is expected to be awarded by September,12 | 13 Bid received and are under Evaluation. Contract is expected to be awarded by September,12 | - | Contract awarded on 29.03.2012. | Bid has been opened on 30.05.2012 and under Evaluation. | ||
6. | Date of completion | Target | Dec’ 2015** | Dec’ 2015** | Dec’ 2015** | Dec’ 2016** | Mar’17 | Dec’2013 |
Achievement | ||||||||
7. | Remarks |
**Civil work is expected to be completed by Dec’15 except some work required for commissioning by Dec’16.
Progress of work on Dedicated Freight Corridor
Sl.No. |
Name of Package |
Name of Package1 |
Name of Package2 |
Name of Package3 |
Name of Package4 |
Name of Package 5 (MIS) |
Name of Package 6 |
|
---|---|---|---|---|---|---|---|---|
Particulars |
Length (kms) |
134 |
102 |
106 |
343 |
3338 |
||
1. |
Cost |
Estimated* |
- |
- |
- |
- |
- |
|
Awarded |
23.97 |
|||||||
2. |
Land Acquisition (in ha) |
Target |
484 |
360 |
476 |
- |
- |
|
Achievement |
- |
- |
- |
- |
||||
3. |
Date of Issue of RFQ |
Target |
Issued |
Oct’ 2012 |
Issued |
|||
Achievement |
- |
|||||||
4. |
Date of Issue of RFP |
Target |
Issued |
Dec’ 2012 |
||||
Achievement |
- |
Apr’ 2012 |
||||||
5. |
Date of Award of Contract |
Target |
Sept’ 2012 |
Sept’ 2012 |
Sept’ 2012 |
Sept’ 2013 |
Mar’13 |
Jun’ 2012 |
Achievement |
||||||||
6. |
Date of completion |
Target |
Dec’ 2015** |
Dec’ 2015** |
Dec’ 2015** |
Dec’ 2016** |
Mar’17 |
Dec’2013 |
Achievement |
||||||||
7. |
Remarks |
|||||||
*The base construction cost of APL-1 (Bhaupur - Khurja section of EDFC) has been estimated as Rs.4689 Crs. The estimates are tentative and not based on detailed designs. |
Progress on DFC against Targets for 2012-13 (Western Corridor)
(Progress as on 30.06.2012)
Sl.No. |
Name of Package |
Name of Package1 |
Name of Package2 |
Name of Package3-A |
Name of Package3 |
Name of Package4 |
Name of Package 5 |
Name of Package (Construction of 54 Bridges Vaitarna – Bharuch) |
|
---|---|---|---|---|---|---|---|---|---|
Particulars | Length (kms) | 283 | 342 | - | 290 | 915 | - | ||
1. | Cost (Rs. In crore) |
Estimated* | - | - | - | - | 604 | ||
Awarded | |||||||||
2. | Land Acquisition (in ha) | Target | 1185 | 924 | 396 | 1102 | - | - | - |
Achievement | 1143 | 924 | 48 | 980 | |||||
3. | Date of Issue of RFQ | Target | Issued | Issued | Issued | Jun’2012 | Aug’2012 | Sept’2012 | |
Achievement | RFP issued on 22.06.2012 | - | - | ||||||
4. | Date of Issue of RFP | Target | Jun’2012 | Jun’2012 | Sep’2012 | Sept’2012 | Jan’2013 | Feb’2013 | |
Achievement | RFP issued on 30.06.2012 | RFP issued on 30.06.2012 | - | - | - | - | |||
5. | Date of Award of Contract | Target | Nov’ 2012 | Nov’ 2012 | Mar’2013 | Mar’2013 | Sep’2013 | Sep’2013 | Feb’2009 |
Achievement | |||||||||
6. | Date of completion | Target | Jun’2016 | Jun’2016 | Mar’ 2016 | Apr’2017 | Mar’2017 | Mar’2017 | Dec’2013 |
Achievement | |||||||||
7. | Remarks |
* The base construction cost of Phase-1 (Rewari-Vadodara Section of WDFC) has been estimated as 15143 Crs. The estimates are tentative and not based on detailed designs.
**Civil work is expected to be completed by Dec’15 except some work required for commissioning by Dec’16.
PROGRESS/ACHIEVEMENT OF THE MONITORABLE TARGETS SET BY PLANNING COMMISSION FOR DFC FOR 2010-11
DFC: Progress upto Quarter-2 (2011-12) |
||||
---|---|---|---|---|
Activity |
Cumulative Target upto end of Q2 |
Cumulative Progress upto |
||
Western DFC |
||||
A) Phase I (Rewari-Vadodara) – 930 km |
||||
A1) Phase-I (Re-Vadodara) ( 794 Km.) except Iqbalgarh-Kalol section |
||||
Progress of Land Acquisition: |
||||
|
794 |
Completed |
||
|
794 |
790 ( 4 kms of Rewari district is under final stage of notification) |
||
|
794 |
764 (26 kms of Rewari in final stage of 20 F, 4 km in sensitive area in Anand, Gujarat where Competent Authority has suggested to move cautiously. This would be covered by next Quarter) |
||
A2) Phase-I, Revised Alignment (136 Km) Iqbalgarh-Kalol section |
||||
|
100 |
84( Due to slight public resentment in Mehsana district, notification delayed . Now notification in final stage o publication) |
||
A3) Finalizing PQ for Civil Works – Package 1 and 2 |
To be Completed |
PQ discharged due to conflict of interest. NOC/Approval for re invitation of PQ is awaited from JICA. |
||
A4) Issue of Bid document for civil works – Package 1 and 2 |
To be Completed |
At final stage of preparation. |
||
B) Phase II (JNPT-Vadodara, Rewari-Dadri and TKD-Pirthala – 569 km) |
||||
B1) Progress of Land Acquisition: |
||||
|
569 |
524 (20A lapsed due to the change in Competent Authority by State Govt.) |
||
|
250 |
267 |
||
|
120 |
112 (As per JICA policy 20 F to be issued after RRP completion which is targeted for November 2011) |
||
B2) EIA |
To be completed |
EIA report is under preparation with JICA Study – target November 2011. |
||
C) Vaitarna – Bharuch section of Western DFC (Construction of 54 major and important bridges) |
||
C1) Physical Progress (Cumulative) |
32% |
30% |
EASTERN DFC |
||
D) APL – 1 (343 Kms ) Khurja – Bhaupur |
||
D1) Progress of Land Acquisition: |
||
|
343 |
343 (Completed) |
|
300 |
343 (Above Target) |
|
270 |
270 (Completed) |
D2) EIA |
Target was Q1 |
Completed. |
D3) RAP |
Target was Q1 |
Completed. |
D4) World Bank Board approval for loan |
Target was Q1 |
Loan Approved |
D5) Issue of Civil bid document. |
Target was Q1 |
Bid Document sent to the WB for clearance on 10.10.2011. |
E) APL – 2 (393 Kms ) Bhaupur – Mughalsarai Section |
||
E1) Progress of Land Acquisition: |
||
|
393 |
393 (Completed) |
|
393 |
393 (Completed) |
|
280 |
356 |
F) APL – 3 (447 Kms ) Ludhiana – Khurja – Dadri Section |
||
F1) Ludhiana – Khurja (404 Kms) |
||
a) Progress of Land Acquisition: |
||
|
404 |
404 (Completed) |
|
350 |
350 (Completed) |
|
50 |
161 (Above Target) |
b) EIA |
To be Completed |
EIA report submitted to WB for clearance, changes suggested by World Bank due to minor change in alignment from detour to parallel under process. |
c) RAP |
To be Completed |
EIA report submitted to WB for clearance, changes suggested by World Bank due to minor change in alignment from detour to parallel under process. |
F2) Khurja-Dadri Section (43 Kms) |
||
a) Progress of Land Acquisition: |
||
|
43 |
43 (Completed) |
|
43 |
43 (Completed) |
G)Railway Funded (118 Kms) Mughalsarai - Sonnagar Section |
||
G1) Progress of Land Acquisition: |
||
|
118 |
118 |
|
85 |
80 (Due to slight public resistance in Chandauli parallel alignment) |
|
30 |
57 (Above Target) |
G2) Physical Progress of civil work |
52% |
53% (Above Target) |
G3) Issue of Civil Bid document |
Targetted for Q2 |
Not Achieved |
G4) Issue of system bid document |
Targetted for Q2 |
Not Achieved |
H) Sonnagar – Dankuni Section ( 538 Kms) |
||
H1) Progress of Land Acquisition: |
||
|
25 |
Due to sensitive nature, “A” category objections - cautious approach adopted. Now the proposal has been cleared by Competent Authority and is under process of notification. |