Ministry of Railways: Operational Targets

Progress on Monitorable Targets for the First Quarter of 2012-13

Program Year Cummulative Targets and Progress Apr May Jun* Remarks/Reasons for Shortfall in Q1
Originating Loading (Million Tonnes) 2012-13 Target 81 164.5 246 IIP indices show 3,4% growth in core sector industries in May-June 2012. 
  Achievement 80.25 164.38 244.81
2011-12 Actual     233.66
Freight NTKMS (Billions) 2012-13 Target 53.643 108.942 162.916
  Achievement 51.553 104.951 156.269
2011-12 Actual     154.5
Originating Passengers (Millions) 2012-13 Target 690.86 1414.33 2141.49 Minor Shortfall due to drop on sub urban section of Central Railway due to discruption of traffic on 3 days in April. In Mar, 2012 6% additional pasengers opted for montly/quarterly seasons tickets in anticipation of rise in fares.
  Achievement 686.29 1379.93 2103.01
2011-12 Actual     2039.82
PKMs (Billions) 2012-13 Target 88.309 180.786 273.736
  Achievement 90.71 181.99 275.9
2011-12 Actual     261.83
New Lines (Kms) 2012-13 Target     24  
  Achievement     24
2011-12 Actual     95
Doublings (Kms) 2012-13 Target 18 33 69 Due to slow progress by the executing agencies
  Achievement 18 43 54
2011-12 Actual     20
Gauge Conversion (TKM) 2012-13 Target 41 59 92 Due to slow progress by the executing agencies
  Achievement 41 59 59
2011-12 Actual     36
Electrification Projects (for Tracks) (RKM) 2012-13 Target 20 80 150 Slippage in achieving the target is due to shortage of Material (Steel and Copper). 
  Achievement 18 18 78
2011-12 Actual     68
Workshops including Production Units (In Rs. crore) 2012-13 Target 75 150 250 Minor shortfall: Will be made good in the coming months.
  Achievement 77.35 136.17 238.58
2011-12 Actual 130.16 184.34 261.06
Metropolitan Transport Project (In Rs. crore) 2012-13 Target 142.03 284.03 473.36 Achievement upto May 2012. Acquisition of land and delay in clearances from Civil authorities. 
  Achievement 16.04 81.09 81.09
2011-12 Actual     109.39
Rolling Stock 
Locomotives (Nos.) 2012-13 Target 44 95 146 Shortfall in production of diesel locomotives is due to supply chain issues. The shortfall will be made good during the year. The production of locos is, in fact, more than last year's 1st Qtr.
  Achievement 39 81 132
2011-12 Actual 32 71 115
Wagons (Nos.) 2012-13 Target 1000 2200 3500 Annual Target for this year is 16000 compared to 18000 of last year
  Achievement 1722 2949 4162
2011-12 Actual 1810 3648 5219
Coaches (Nos.) 2012-13 Target 198 495 794  
  Achievement 207 526 847
2011-12 Actual 247 508 822
* Provisional 

Progress on Monitorable Targets for the 2nd  Quarter of 2012-13

Program Year Cummulative Targets and Progress 1st Qrt July August September Remarks/Reasons for Shortfall in Q2
Originating Loading (Million Tonnes) 2012-13 Target 246 328.75 409.94 489.44 The IIP indices for April- August 2012 show a growth of  2.8% as  compared to 5.5% growth in April-August 2011
Achievement 244.81 327.02 405.54 481.45
2011-12 Actual 233.66 313.32 389.09 459.36
Freight NTKMS (Billions) 2012-13 Target 162.916 217.716 271.487 324.14
Achievement 156.269 208.489 260.008 309.819
2011-12 Actual 154.5 206.63 257.728 305.906
Originating Passengers (Millions) 2012-13 Target 2141.49 2853.84 3560.27 4282.99 Marginal Shortfall is on account of drop in growth in number of passengers on the suburban section of Central, Western and Eastern Railways.
Achievement 2131.05 2844.01 3567.51 4274.87
2011-12 Actual 2039.82 2732.26 3418.36 4120.75
PKMs (Billions) 2012-13 Target 273.736 364.81 455.11 558.64
Achievement 285.3 371.88 464.56 554.51
2011-12 Actual 261.83 355.6 443.4 531.2
New Lines (Kms) 2012-13 Target 24 24 24 76 Due to failure of contracts.
Achievement 24 24 41 41
2011-12 Actual 95 121 121 121
Doublings (Kms) 2012-13 Target 69 69 92 142 Due to heavy monsoon and failure of contracts.
Achievement 54 54 93.1 120.1
2011-12 Actual 20 32 51 123
Gauge Conversion (TKM) 2012-13 Target 92 92 92 103 Due to heavy monsoon.
Achievement 59 59 70 70
2011-12 Actual 36 47 163 163
Electrification Projects (for Tracks) (RKM) 2012-13 Target 150 220 330 450 Slippage is due to shortage of Material (steel). However, it is 12.15% more than last year. The target is likely to be made good in Q3 and Q4.
Achievement 78 83 168 323
2011-12 Actual 68 68 89 288
Workshops including Production Units (In Rs. crore) 2012-13 Target 250 335 425 515 The Figure for Sept 2012 is not yet available but as per trends in the preceeding month, the target is likely to be surpasssed
Achievement 238.58 331.87 480.7 NA
2011-12 Actual 261.06 326.03 428.65 527.41
Metropolitan Transport Project (In Rs. crore) 2012-13 Target 473.36 757.33 1041.3 1419.93 The Figure for Sept 2012 is not yet available. Acquisition of land and delay in clearances from Civil authorities.
Achievement 81.09 277.04 399.47 NA
2011-12 Actual 109.39 246.07 267.33 368.85
Rolling Stock 
Locomotives (Nos.) 2012-13 Target 146 197 249 301 Shortfall is marginal. Will be made good.
Achievement 132 187 242 298
2011-12 Actual 115 164 209 259
Wagons (Nos.) 2012-13 Target 3500 4800 6100 7500 Above Target, Yearly target less than that of last year
Achievement 4162 5247 6956 8831
2011-12 Actual 5219 7321 9117 10752
Coaches (Nos.) 2012-13 Target 794 1100 1398 1702 Above Target
Achievement 847 1183 1520 1852
2011-12 Actual 822 1101 1380 1666