Annual Report on the Working of
State Electricity Boards and Electricity Department, April 1999
Power and Energy Division, Planning Commission

Table 3.2
Addition to Installed Capacity (MW)

8th Plan Target 8th Plan Achievement 9th Plan Target 1997-98 Actuals 1998-99 Target
I. Mode
Hydel

9282.0

2427.65

9819.7

233.0

544.5

Thermal

20156.0

13554.8

29545.5

2993.5

2754.8

Nuclear

1100.0

440.0

880.0

0.0

0.0

Total

30538.0

16422.4

40245.2

3226.5

3299.3

II. Ownership
State

14780.0

6773.0

10747.7

1676.0

1278.0

Central

12858.0

8387.0

11909.0

333.0

191.3

Private

2810.0

1262.4

17588.5

1217.5

1830.0

Total

30538.0

16422.4

40245.2

3226.5

3299.3